Our Projects

We conduct project to make our services more reliable to our clients and also making the access of water to all parts of the Coast Region.

Our World Bank Projects

Supply of water to Ngomeni fish landing site in Kilifi county -Contract no. CWWDA/T/KLF/W/018/2021-2022 World Bank Projects Works

Contract NameContract ScopeStatus

Supply of water to Ngomeni fish landing site in Kilifi county.

Contract no. CWWDA/T/KLF/W/018/2021-2022

1.Preliminary and General Items
-Contractual Requirements and Performance requirements.
2.Pipelines
-12km Laying of Gravity mains 160mm HDPE Pn10 and associated fittings.
-Installation of air release valves  - 25nr and Washouts  - 27nr with associated  fittings.
-Bulk meters double flanged - 2nr and Zonal meters 5nr.
- Chambers for air valves and washouts 52nr.
- Distribution lines 90mm hdpe 1,000m.
- Distribution lines 63mm hdpe 2,000m.
- Micro-tunnelling pipes across highway.
3.Reinforced concrete tower 6m high  -1nr
- Construct Concrete towers 1nr.
- Install 2No.x10,000L plastic tanks on 1nr concrete tower
50% 

Kenya Towns Sustainable Water Supply and Sanitation Program World Bank Projects

Main Contract NamesContract ScopeStatus
Pemba Dam RehabilitationConstruction of New WTP .Rehabilitation of the Weir Interconnection of the existing system.
Improve supply by adding 3000m3 per day to Kwale, Kinango, Likoni and Mombasa via Changamwe.
-100% physical progress
-Commissioning & testing ongoing
Changamwe Repooling-9.8km of sewers
-260 Man holes
-25% complete
Watamu Water Distribution Network Works -66% physical progress/75% of elapsed time

Improvement of Drinking Water and Sanitation Systems in Mombasa World Bank Projects

Main Contract NamesContract ScopeStatus
Mwache WTP-Raw water pumping station
-186,000 m3/d WTP
-Clear Water Tanks
-Preliminary Design Studies Completed
-NOL for Prequalification Docs obtained
Mwache SML Transmission Line and Terminal Tank-28 km of Transmission line
- 28,000 m3 Tank at Dongo Kundu
-Draft Detailed Design Completed
-Draft Prequalification Docs Completed
Mwache WML Transmission Line and Terminal Tanks-12 km of Transmission line
- 14,000 m3 Tank at Bonje & 16,000 m3 Changamwe Birikani
-Draft Detailed Design Completed
-Draft Prequalification Docs Completed
Mwache NML Transmission Line and Terminal Tank-22 km of Transmission line
- 14,000 m3 Tank at Nguu Tatu
-Draft Detailed Design Completed
-Draft Prequalification Docs Completed
SML & WML Distribution Network-Water Distribution Network (66 km)-Bids docs submitted submitted on 10th Jan 23 
NRW Works (MOWASCO)DMAs ImplementationProcurement of Consultant ongoing at RfP stage
Likoni Emergency Works -Works contract singed on 15th August 2021
-24% physical progress/95% of elapsed time

Water and Sanitation Development Project (WSDP) World Bank Projects

Main Contract NamesContract ScopeStatus
Baricho Replacement Boreholes-Boreholes 1,3 & 4
-Drilling & Equipping
-Local Protection Works
-Completed and on DLP
Mombasa North Mainland Lot 1A-Water Distribution Network (88 km)-Contract signed on 23rd March 2021
-87% physical progress
North Mainland Nyali Phase 1-Water Distribution Network (65 km)-Contract signed on 23rd March 2021
-51% physical progress/117% of elapsed time
Baricho Protection Works-Gabion Works
-4km of Piling Works
-8,950 m2 of Access Road
-Contract signed on 17th Nov 2021
-85% physical progress
Second Baricho Kakuyuni Line-29 km of 800mm pipeline
-5,000 m3 tank at Kakuyuni
-3 pump sets &  Electromechanical works
-Contract signed on 13th April 2022
-20% physical progress