Our Projects

We undertake development projects to make our services more reliable to our clients and also making the access of water to all parts of the Coast Region.

Our Ongoing Projects

Kenya Towns Sustainable Water Supply and Sanitation Program

Main Contract NamesContract ScopeStatus
Pemba Dam RehabilitationConstruction of New WTP .Rehabilitation of the Weir Interconnection of the existing system.
Improve supply by adding 3000m3 per day to Kwale, Kinango, Likoni and Mombasa via Changamwe.
-100% physical progress
-Commissioning & testing ongoing
Changamwe Repooling-9.8km of sewers
-260 Man holes
-25% complete
Watamu Water Distribution Network Works -66% physical progress/75% of elapsed time

Improvement of Drinking Water and Sanitation Systems in Mombasa AFD Projects

Main Contract NamesContract ScopeStatus
Mwache WTP-Raw water pumping station
-186,000 m3/d WTP
-Clear Water Tanks
-Preliminary Design Studies Completed
-NOL for Prequalification Docs obtained
Mwache SML Transmission Line and Terminal Tank-28 km of Transmission line
- 28,000 m3 Tank at Dongo Kundu
-Draft Detailed Design Completed
-Draft Prequalification Docs Completed
Mwache WML Transmission Line and Terminal Tanks-12 km of Transmission line
- 14,000 m3 Tank at Bonje & 16,000 m3 Changamwe Birikani
-Draft Detailed Design Completed
-Draft Prequalification Docs Completed
Mwache NML Transmission Line and Terminal Tank-22 km of Transmission line
- 14,000 m3 Tank at Nguu Tatu
-Draft Detailed Design Completed
-Draft Prequalification Docs Completed
SML & WML Distribution Network-Water Distribution Network (66 km)-Bids docs submitted submitted on 10th Jan 23 
NRW Works (MOWASCO)DMAs ImplementationProcurement of Consultant ongoing at RfP stage
Likoni Emergency Works -Works contract singed on 15th August 2021
-24% physical progress/95% of elapsed time

Water and Sanitation Development Project (WSDP) WSDP Projects

Main Contract NamesContract ScopeStatus
Baricho Replacement Boreholes-Boreholes 1,3 & 4
-Drilling & Equipping
-Local Protection Works
-Completed and on DLP
Mombasa North Mainland Lot 1A-Water Distribution Network (88 km)-Contract signed on 23rd March 2021
-87% physical progress
North Mainland Nyali Phase 1-Water Distribution Network (65 km)-Contract signed on 23rd March 2021
-51% physical progress/117% of elapsed time
Baricho Protection Works-Gabion Works
-4km of Piling Works
-8,950 m2 of Access Road
-Contract signed on 17th Nov 2021
-85% physical progress
Second Baricho Kakuyuni Line-29 km of 800mm pipeline
-5,000 m3 tank at Kakuyuni
-3 pump sets &  Electromechanical works
-Contract signed on 13th April 2022
-20% physical progress